How we build

A clear path from first call to first swim.

Most concrete pools take 12–16 weeks. Our 6-stage process is transparent at every step — you know what's happening, when, and why.

12+Years in Melbourne
BH&GFeatured Publication
VBARegistered Builder
2012Established

The Process

From first call to first swim.

A transparent 6-stage process. Most builds complete in 12–16 weeks.

01Week 0

Consultation

Phil visits your property to understand your vision, assess the site, and answer your questions.

02Weeks 1–3

Design & Quote

Custom architectural design tailored to your home, lifestyle, and budget. Fully itemised quote.

03Weeks 2–4

Council Approval

We handle VBA-required permits, drawings, and submissions to your council.

04Weeks 4–8

Excavation & Shell

Site prep, excavation, reinforced steel, and concrete shell construction.

05Weeks 8–14

Finishing & Systems

Interior finish, waterline tile, coping, plumbing, electrical, filtration.

06Weeks 14–16

Commissioning

Water fill, chemistry, final inspection, compliance certification, walkthrough.

Every step explained

Here's exactly what happens, week by week

No jargon, no surprises. This is the same roadmap we walk through in your free consultation.

Stage 1

Week 0

Free On-Site Consultation

Phil visits your property personally. No sales pitch — just a genuine conversation about your vision.

  • Site access assessment (machinery, excavation logistics)
  • Understanding your lifestyle: fitness, family, entertaining
  • Discussing realistic budget ranges on your site
  • Early thinking on shape, size, finish, and features
  • Timeline guidance based on current build schedule

Stage 2

Weeks 1–3

Custom Design & Itemised Quote

Concept design tailored to your home and site, followed by a fully itemised quote.

  • Bespoke concept design drawings
  • Material and finish recommendations with samples
  • Systems specification (filtration, heating, lighting)
  • Line-itemised quote — no lump sums, no surprises
  • Payment schedule aligned with construction milestones

Stage 3

Weeks 2–4 (concurrent with design)

Council Approval & Engineering

We handle permits, drawings, and VBA submissions. You don't touch the paperwork.

  • Structural engineering for your specific soil profile
  • VBA-required Building Permit preparation
  • Submission to your local council
  • Follow-up with authorities through approval
  • Heritage overlay / setback navigation where required

Stage 4

Weeks 4–8

Excavation & Concrete Shell

The most visible phase. Machines arrive, pool shell is formed, reinforced, and concreted.

  • Site preparation and access protection
  • Excavation to engineered depth and tolerances
  • Sub-floor drainage install
  • Steel reinforcing placement (150mm above-ground formwork)
  • Concrete pour with specified PSI rating
  • Cure and initial testing

Stage 5

Weeks 8–14

Interior Finish, Coping & Systems

The stage where your pool starts looking like a pool — and all the clever systems go in.

  • Interior finish (plaster / pebblecrete / quartz / tile)
  • 300mm ceramic waterline tile
  • Coping tile install (travertine, bluestone, or spec)
  • Filtration, pumps (Serenity Smart available)
  • Plumbing and electrical rough-in
  • Lighting install (LED or fibre-optic)
  • Heating integration (if specified)

Stage 6

Weeks 14–16

Commissioning & Handover

Final inspection, water fill, chemistry, and compliance sign-off.

  • Water fill and initial chemical balance
  • System commissioning and pressure testing
  • AS1926 barrier compliance inspection
  • Form 23 Compliance Certificate issued
  • Full client walkthrough and operation training
  • Warranty documentation handed over
  • Ongoing maintenance options (Serenity Clear)

Words

From our clients

Phil and his staff showed a professional and prompt attitude to their work, which resulted in us achieving a beautiful pool, perfect for our lifestyle and family. Serenity Pools reliability and commitment to our project has been very impressive and appreciated.
Melinda & Nick MoreyHampton, VIC
From the day of excavation to the completion, Phil exceeded our expectations. He gave great attention to detail to the whole pool construction, listening to our needs, concerns and ideas, so that we achieved a pool that we are extremely happy with.
Andrew PrestonBox Hill, VIC
We would highly recommend Serenity Pools to anyone. The entire experience from design through to completion was seamless. Phil's expertise and attention to detail made all the difference to the final result.
Janine & Mark LynchParkdale, VIC

Ready to start stage one?

Book your free on-site consultation with Phil. No obligation, no sales pitch — just a conversation about your project.

Call PhilConsultation